Features at a
Glance

Ø
Forward
scheduling: Front load your shop from the manufacturing
order release date
Ø
Backward
Scheduling: JIT method by scheduling backwards from the Due
Date to determine when you need to start in order to deliver
just in time to meet demand
Ø
Throughput
Scheduling: The system automatically identifies the bottleneck
in the work flow and subordinates all other operations to flow
through the bottleneck. This minimizes Queue and Work In
Process (WIP).
Ø
Infinite
Scheduling: Ability to run a global infinite schedule, a job by
job infinite schedule, and/or an operation by operation
infinite schedule to determine demand
Ø
Finite
Scheduling: Will not overbook resources (unless individual jobs
or operations have been assigned as infinite)
Ø
Critical
Ratio: Can produce a schedule that takes into account lead time
demand and hours of effort required to determine the jobs
overall priority in the shop so you know when you need to start
work to meet the promises date
Ø
A powerful
integration module allows for on line user defined control for
interfacing to other systems.
Ø
Alternate
Schedules: User Defined Schedules based on user defined
criteria. For example, least time to manufacture, First in
First Out (FIFO) and Last in First Out (LIFO). Most
importantly, DMS helps you avoid FISH (First In Still Here)
Ø
Multiple
resource profiles give you the flexibility to set up a variety
of Resource capabilities for realistic overtime options. This
gives you the power to run quick simulations in order to
determine the best plan to meet demand!
Ø
Advanced
Router Control logic that enables you to model very complex
work flow rules
Ø
Min/Max value
for labor and machine allocation. This enables the scheduling
engine to select an optimum high level schedule. After the
schedule has been developed the DMS Planning Board can be used
to easily adjust where labor and machine load is being used.
Ø
Advanced
Project Oriented features such as being able to schedule by
Duration (in days) and by planned hours. For example the
duration of a task may be 10 days but the actual labor time
required may only be 10 hours.
Ø
Option to use
project management type commands such as Finish to Finish,
Start to Start with lead time and/or lag time,
etc. Or you
can use schedule commands such as parallel, sequential,
lot (to pass lot sizes), and more.
Ø
DMS allows
for multiple calendars to be used for both scheduling and for
assessing load against capacity. This gives the capability to
perform quick “what if” scenarios, running different OT options
for best results
Ø
The DMS “Job
Completions” module has the capability of accepting both an
electronic flat file and manual entry to calculate and show
completion information to Work In Process. Percent complete can
be based on either quantities complete (specific to the
operation if required) or time complete against planned time.
This gives all shops the ability to view the exact status of a
job and the Actual start and completion of the job and its
operations.
|